Hwy 53 Project Update 7-12 to 7-24
Traffic impacts

Work of July 12 – 17
Memorial to 20th Street (Stage 2)
- Manhole cover work
- Striping
- Detour removed and reopen to traffic July 15
15th Street to Industrial Ave. (Stage 3C)
- Detour removed and currently open to traffic
Industrial Ave. to 10th Street (Stage 3A)
- Begin storm sewer work on east side
- West lane open to traffic
Hwy 11 to Border
- Begin removals on north end July 13
Work of July 19 – 24
Access Road
- Removals and grading from north end moving south
- Business access from the south
Crescent Dr.
- Entrance culvert work
- Business access from north and south
Industrial Ave. to 10th Street (Stage 3A)
- Continue storm sewer work east side
- Westlane open to traffic.
Hwy 11 to Border
- Continue removals north to south