Hwy 53 Construction Project Update

Hwy 53 Construction Project Update

August 3, 2021 News -- KSDM-KGHS 0

Traffic impacts

A rendering of the Hwy 53 International Falls project.

Work of August 2 – 7

Access Road (Stage 2)

  • Grading from Memorial Dr to Days Inn

Crescent Dr. (Stage 2)

  • Grading and entrance culvert work

Access Rd to 20th Street (Stage 2)

  • Finish 10’ bituminous walk

15th Street to Industrial Ave. (Stage 3C)

  • Finish 10’ bituminous walk

Industrial Ave. to 10th Street (Stage 3A)

  • Grading on the west half
  • East half open to traffic

Hwy 11 to Border

  • No work